Preparation before installation includes:
1) Check the mechanical seal models and
specifications to meet the requirements of design drawings, all parts
(especially the sealing surface, secondary seal) for damage, deformation,
cracks and other phenomena, if the defect must be replaced or repaired.
2) Check the mechanical seals with the size
of the parts, roughness, parallelism with the design requirements.
3) The use of a small spring
mechanical
seals, check the length and rigidity of small springs are the same.
4) Check the host shaft runout, wobble and
deflection amount meets the technical requirements, the sealed chamber meets
the installation size, the seal faces and the shaft is perpendicular to the
general requirements: a shaft runout is not more than ± 0.5mm; axis wobble
amount (rotating ring seal ring)
Not more than 0.06mm; axis maximum
deflection is not more than 0.05mm; Seals and gaskets contact plane is not
perpendicular to the centerline of the allowable difference of 0.03 ~ 0.05mm.
5) The installation process should be kept
clean, especially the rotating ring and stationary ring seal face and secondary
seal surface should be free magazine, dust. Wipe the sealing surface is not
allowed with a dirty cloth.
6) Installation tools are not allowed to
beat the sealing elements to prevent the seal from being damaged.
views:806 lable:installation of mechanical seals,mechanical seal,mechanical seals,